RERA 70% Account and CA Certificates for Builders in Gujarat 2026: Withdrawal Certificates, Annual Audit by 30 September and Penalty for Misuse

Admin
17 November 2026
RERA GUJARAT
1
RERA 70% Account and CA Certificates for Builders in Gujarat 2026: Withdrawal Certificates, Annual Audit by 30 September and Penalty for Misuse

Builders in Gujarat must keep 70% of buyers' money in a separate RERA account and need a CA certificate for every withdrawal from it.

Nileshbhai is building 48 flats in a GujRERA-registered project in Junagadh with an estimated cost of Rs 18 crore. Bookings have brought in Rs 6 crore. To pay a land instalment and a cement supplier, he withdrew Rs 1.5 crore from the RERA account on a letter from his site engineer alone. His bank now wants architect, engineer and CA certificates before the next withdrawal, and the annual audit of the project accounts for 2025-26, due by 30 September, has not been done.

RERA registration is only the start for a builder. The money rules run for the life of the project, and they are what banks and GujRERA look at first when buyers complain. Here is how they work in 2026.

Short Answer: Under RERA, a promoter must deposit 70% of the amounts collected from buyers of a registered project in a separate account in a scheduled bank, and use it only for the land and construction cost of that project. Money can be withdrawn only in proportion to the completion of the project, as certified by an engineer, an architect and a chartered accountant in practice. The project accounts must also be audited every year by a practising CA within six months of the year end, that is by 30 September, with a statement that the money was used for the project. Breaking these rules can lead to a penalty of up to 5% of the estimated project cost.

Our team issues RERA withdrawal certificates and carries out the annual audit of project accounts for builders. Call or WhatsApp +91 82005 28355, or see the details at the end of this guide.

The 70% rule

  • Which money: all amounts realised from buyers of the project, including bookings and instalments.
  • Where it goes: 70% is deposited in a separate account in a scheduled bank, one for each project.
  • What it can pay for: only the land cost and construction cost of that project.
  • The other 30%: stays outside the RERA account, but it is still project money and must be accounted for properly.
  • Bank directions: GujRERA has issued directions on how project accounts are operated, so check the current ones before opening or changing an account.
  • Registration first: the account details are given when the project is registered. See RERA Gujarat registration and QPRs.

Withdrawals and the CA certificate

  • In proportion to completion: money can be taken out only to the extent the project is complete.
  • Three certificates: the engineer and the architect certify the stage of completion, and a practising CA certifies the cost incurred and the amount that may be withdrawn.
  • What the CA checks: land and construction cost actually paid, collections from buyers, earlier withdrawals and the statements of the account.
  • Papers to keep: land documents and payments, contractor and supplier bills, payment proof, the sales register and the architect's and engineer's certificates.
  • Format: certificates follow the formats GujRERA prescribes and carry the CA's UDIN.

Annual audit of project accounts

  • Every year: the project accounts are audited by a practising CA within six months of the end of the financial year, that is by 30 September.
  • The statement: the CA signs a statement of accounts verifying that the money collected for the project was used for it, and that withdrawals were in proportion to completion.
  • Submitted to GujRERA: the audited statement is uploaded on the GujRERA portal.
  • Separate from other audits: it is project-wise, and different from the company's statutory audit and the tax audit. See audit for private limited companies.

Other money rules for builders

  • Quarterly progress reports: filed on the GujRERA portal every quarter, with booking and construction details.
  • TDS by buyers: buyers of flats worth Rs 50 lakh or more deduct 1% TDS, which must be matched with their payments. See TDS on buying property.
  • GST on flats: 1% or 5% on under-construction units, and none on ready flats. See GST on flats in Gujarat.
  • Landowners: joint development agreements bring their own tax timing. See joint development agreements.
  • Plotted schemes: NA plots sold in a registered scheme follow the same account rules. See NA plots and GujRERA.

Common mistakes

  • Depositing buyers' cheques in the general account first, and moving the money later or not at all.
  • Withdrawing on the engineer's letter alone, without the architect's and CA's certificates.
  • Using RERA account money for another project or for buying new land.
  • Counting expenses of other projects as this project's cost.
  • Missing the 30 September audit, or getting it signed without a project-wise reconciliation.
  • Leaving buyers' TDS and cancellation refunds unreconciled.

Penalties and complaints

  • Penalty: breaking the conditions given at registration, including the 70% account, can attract a penalty of up to 5% of the estimated project cost.
  • Buyers' complaints: buyers can complain to GujRERA, which can call for the accounts and certificates.
  • Bank checks: banks may ask for the certificates before allowing withdrawals.

Back to Nileshbhai. His architect and engineer certify the stage of completion, and the CA works out what he could have withdrawn from the land and construction cost actually paid. The Rs 1.5 crore he took out turns out to be Rs 40 lakh more than the eligible amount, so he puts the excess back into the RERA account. From now on, each withdrawal goes with all three certificates. The overdue annual audit for 2025-26 is completed and uploaded, and the TDS deducted by his buyers is matched with their payments.

How we help

  • CA certificates for withdrawals from the RERA account
  • Annual audit of project accounts and the statement of accounts
  • Project-wise accounting and bank set-up
  • Reconciling buyers' payments, TDS and GST
  • GujRERA registration, quarterly reports and the compliance calendar
  • Income tax and GST for builders and landowners

Gadhia Associate has been in practice since 2007 and has handled work for over 7,000 clients, with a 5.0 Google rating from more than 100 reviews. Builders and developers from Junagadh, Rajkot, Keshod, Veraval and Porbandar come to our Junagadh office, where same-day appointments are available. Projects elsewhere in Gujarat are handled online.

Running a GujRERA project? Keep withdrawals and the annual audit in order before buyers or GujRERA ask. Call or WhatsApp +91 82005 28355, or message us on WhatsApp. The first consultation is free.

Frequently asked questions

What is the 70% rule under RERA?

Builders must keep 70% of buyers' payments for a registered project in a separate bank account and use it only for that project's land and construction cost.

Who issues the certificate for withdrawal from the RERA account?

A practising chartered accountant, together with the project's engineer and architect, who certify the stage of completion.

When is the RERA annual audit due?

Within six months of the end of each financial year, that is by 30 September.

Can a builder use RERA account money for another project?

No. It can be used only for the land and construction cost of the same project.

What is the penalty for misusing the RERA account?

Up to 5% of the estimated cost of the project, and GujRERA can act on buyers' complaints.

Is the RERA audit the same as the tax audit?

No. It is a separate, project-wise audit of the RERA account and the project costs.

Position as of 17 November 2026, under the Real Estate (Regulation and Development) Act, 2016 and GujRERA's rules and directions. GujRERA prescribes the formats and can change its banking directions, so check the current ones for your project.

Need help with GujRERA compliance?

Project and agent registration, quarterly updates, extension applications and compliance audits — handled end to end.

Free first consultation · Mon–Sat, 10am–7pm IST · We work with clients across India

Ready to Simplify Your Taxes and Grow Your Business?

Stop stressing over GST deadlines and complex tax notices. Let the top tax consultancy in Junagadh handle your compliance while you focus on what you do best. Your first consultation is completely free — no hidden fees, no obligations.

Chat with Gadhia Associate via WhatsApp QR

Scan to WhatsApp and chat directly with our tax experts.